The amount of work done with 1991 year:
1. Construction of pile foundation, device retaining walls, strengthening of foundations – more 300 objects.
2. Development and preparation of project documentation – more 100.
3. Testing of soils by piles with static load – more 1600 PC.
4. Technical support, consultation and supervision in the construction of foundations – more 60 objects.
5. Immersion of reinforced concrete piles – more 40 000 PC.
6. Driving Effective Reinforced-concrete Piles – more 10 000 PC.